Kitemu Kisozi Budo Naggalabi SPUR

Contractor: China Railway Seventh Group Co.(CRSG)

Price: UGX 41,613,257,454(VAT inclusive)

Commencement Date: 02 May 2025

Expected completion Date: 02 November 2026

Status: Ongoing

Duration: 18 months plus 12 months DLP

Funded By: World Bank, Agence  Francaise de Developpement {AFD} and Uganda Government

Consultant: Aarvee  Associates in JV with Adriax Consults

Consultancy Amount: UGX  4,765,858,960

Contract Duration: 21 months (Design Review Supervision, DLP)

Contract Signing of Kisozi Kitemu Naggalabi Spur(6.5 KM)