A multi-stakeholder site meeting was conducted on Kitemu–Kisozi Road and Naggalabi Spur Road, bringing together the Chief Administrative Officer (CAO), Resident District Commissioner (RDC), Secretary for Gender, alongside contractors, consultants, and district engineers to assess the progress of ongoing works.
The project currently employs 106 workers on site and has achieved 24.5% physical progress. Implementation remains on course as efforts continue to enhance road infrastructure, improve accessibility, and strengthen service delivery for the benefiting communities.